Why Lagos-Calabar Coastal Highway has flooded sections - Umahi

"Where there is a little depression, water can stay there. I take responsibility for that, and we are going to address it. There is nothing to worry about," he said. The minister also dismissed c

NigerianNewsFeed NewsDesk
By NigerianNewsFeed NewsDesk Admin
@nigerianewsfeed · · 2 min read
Share:fXW
Why Lagos-Calabar Coastal Highway has flooded sections - Umahi
Photo: tribuneonlineng

"Where there is a little depression, water can stay there. I take responsibility for that, and we are going to address it. There is nothing to worry about," he said.

The minister also dismissed claims that the Lagos-Calabar Coastal Highway would be abandoned before completion.

According to him, significant progress has already been recorded within two years of commencement.

"We started in 2024, and this is 2026. Section One, which is 47 km by six lanes, is completed, although the contract duration is three years.

"Section Two, which is 55 km by six lanes, will be substantially completed by November," he said.

Umahi said that construction was also progressing on Sections Three and Four of the highway located in Cross River, Akwa Ibom, Ogun and Ondo states.

He said that difficult terrains, deep swampy areas and environmental considerations had necessitated redesigns and route adjustments in some locations.

"Engineering is dynamic. As we move and encounter difficult swampy terrain, we have to redesign.

"In some places, international environmental standards prevent us from passing through protected forest areas, so detours become necessary," he said.

The minister commended the contractor, Hitech Construction Company, for its commitment to the project, noting that the contractor had continued work on several sections in spite of delayed payments.

Umahi said, "Hitech has continued working on some sections without payment. That demonstrates partnership in national development.

"I do not see more than three companies that can sustain this level of commitment without being paid," he said.

Umahi disclosed that construction was ongoing on other legacy projects, including the Sokoto-Badagry Super Highway and major federal roads across Kebbi, Oyo, Gombe and Akwa Ibom states.

He reiterated the Federal Government's commitment to completing all four legacy road projects initiated under President Bola Tinubu's administration.

"All these projects will not exceed 2031. The four legacy projects will be completed by 2031.

"I am assuring Nigerians that these projects will be delivered. We have Hitech, Infouest, CGC and other reputable contractors working with us," he said.

The minister urged Nigerians to continue supporting and praying for the Tinubu administration to enable it to complete more transformative infrastructure projects across the country. (NAN)

Sources
NigerianNewsFeed NewsDesk
About the Author
NigerianNewsFeed NewsDesk Admin
Trusted, fast and relevant news across Nigeria and beyond.
Read full article
Continue on tribuneonlineng
Visit